• Websites
The honest answer is eight to twelve weeks for most small-business websites, from the first working session to launch. A brand identity and a website together usually take three to four months. Those numbers surprise owners in both directions. Some expect two weeks; some have heard stories about a year. Here is where the time actually goes.
Weeks 1 and 2: discovery
The first stretch is listening. The studio meets your team, walks through the current site, talks to a few customers if possible and agrees on what the site has to do. The output is short: a sitemap, a list of what each page needs and a plan for copy and photos. It feels slow, but it is the part that prevents redesigning the same page three times later.
Weeks 3 to 5: design
Design usually starts with the home page and one or two inner pages, shown on a laptop and a phone. You give feedback, the studio revises, and once the direction is approved the rest of the pages follow faster. Two rounds of changes per page is normal. If you need more than that, the brief or the copy probably needs another look.
Weeks 3 to 7: words and photos
This runs alongside design, and it is where most projects slip. Copy has to be written, reviewed by the owner and sometimes reviewed again by a partner or a lawyer. Photo days get rained out. Menus change. A site cannot launch with gray boxes where the pictures go, so the content schedule matters as much as the design schedule.
If you are writing your own copy, start before the design is finished. The best thing an owner can do to keep a project on time is to deliver the words when they said they would.
Weeks 6 to 10: build
Once pages are approved, the site gets built: templates, forms, booking or menu connections, redirects from your old pages and an editor your team can use. Building is usually the most predictable part of the project. It gets unpredictable when an outside tool, like a reservation or payment system, does not work the way its sales page said.
Weeks 10 to 12: review and launch
The last stretch is testing on real phones and browsers, checking every form, fixing small issues, training your team and pointing the domain at the new site. A careful launch takes a few days, not a few minutes, and it should happen early in the week, never on a Friday afternoon.
What makes a site take longer
- Late content. By far the most common cause. A two-week delay on copy becomes a three-week delay on launch.
- Too many approvers. Each extra decision maker adds a review cycle. Name one person who gives final feedback.
- Scope that grows. “While we are at it” requests are reasonable, but each one moves the date. Keep a list for phase two.
- Missing logins. Domain, hosting, Google and booking accounts. Track them down in week one.
- Integrations. Online ordering, memberships and custom forms take more testing than a simple page.
What can make it faster
A small site with five to eight pages, existing photos and copy that is ready to go can launch in four to six weeks. So can a site built on a proven framework instead of from scratch. Speed comes from fewer decisions and ready materials, not from a studio working nights.
Plan backward from a real date
If you have an opening, a season or an event, count back at least twelve weeks and start there. Tell the studio the date on the first call, and ask to see the schedule in writing, with the dates you owe them content and feedback. A shared calendar with both sides’ deadlines on it is the most useful page in any proposal.